BC, Canada | Fort St. James Green Energy Project 2014 - 2015

 
PROJECT LOCATION: BC, Canada
PROJECT TYPE:

40MW Biomass-fired Electric Generation Facility

MAJOR COMPONENTS:

Siemens Turbine Generator 68 metric tons

Siemens Turbine 60 metric tons

Economizer 58 metric tons

Steam Drum 84 metric tons

Mud Drum 43 metric tons

TOTAL PROJECT VOLUME:

20,818 RVTS

MULTIMEDIA: See Photo Gallery and video

In connection with the project, Iberdrola Spain, contracted WLSC to carry out services such as customs clearance, transportation of heavy and over dimensional equipment, conduct route surveys and all associated transportation of other equipment from various US origins to the project site in Fort Saint James, BC.